Question | Last year, you estimated you would earn $5 million in sales revenues from developing a new product. So far, you have spent $3 million developing the product, but it is not yet complete. Meanwhile, this year you have new sales projections that show expected revenues from the new product will actually be only $4 million. How much should you be willing to spend to complete the product development? a. $0. b. Up to $1 million. c. Up to $4 million. d. Whatever it takes. |
---|---|